Don't answer 'roughly how many person-months?' with a single rough figure
This Qiita article by tsutorm argues that a question about rough effort should not be answered with a single figure such as 'about N person-months'. The author proposes three rules: estimate as quantity × effort per unit, take the effort per unit from past project records rather than guesses, and give the estimate as a range with probabilities.
The article uses screen count as the quantity, since stakeholders can count it, and the effort for batch jobs and APIs is absorbed into the per-screen average. Per-screen effort is past total effort divided by past screen count, a method the author compares to a price per tsubo in house building and calls close to reference class forecasting[1]. Past projects should be recorded in a table with screen count, total effort, duration and notes, and the team should fix its rules for counting screens.
The spread of an estimate narrows as the specification is fixed, a pattern known as the Cone of Uncertainty[2]. Because an estimate is a forecast, the article uses a three-point estimate[3] with optimistic, most likely and pessimistic values, each taken from past records. In the illustrative case (20 screens, 0.4, 0.5 and 0.75 person-months per screen), the range is 8 to 18 person-months, and the expected value, calculated with PERT[4], is 11 person-months, or about 11 million yen at 1 million yen per person-month for a 3-person team. The article advises committing to the line that holds about 80% of the time (about 12.7 person-months), not to the expected value, which is exceeded roughly half the time.
Sources
-
JPQiita JA
「ざっくり工数どのくらい?」に「ざっくり工数このくらい」で答えてはいけない